|
Statement
of Reply from Developers of Wheel Inn Complex.
The first application for
permission on this site, which was for 68 houses, was granted by Cork
County Council subject to a number of conditions and was appealed by Mr.
Neil Jordan and An Taisce. This
appeal proved to be successful and permission was refused by An Bord
Pleanala.
The developer then had revised plans
prepared for a much-reduced development of only 41 houses, no marina and a
much-reduced complex centre and a swimming pool/leisure centre. In preparing those plans the reasons given by An Bord
Pleanala for its refusal were addressed and every effort was made to
minimise the impact of the development on the local environment.
The concerns raised by Mr. Neil Jordan
were also addressed and to this end a meeting was arranged with Mr. Neil
Jordan between Padraig Murphy Consulting Engineer, on behalf of the
developer and by two local independent representatives,
Mr. Denis Regan, Chairman, Beara Action Group and Cllr. Noel
Harrington
An open and frank discussion was held
and the plans of both the earlier application and the revised application,
which at this point in time had been lodged with Cork County Council, were
exhibited to Mr. & Mrs. Jordan.This on 31st
May 2003.
Mr. Jordan has issued statements to the
press and media indicating that he requested a legal covenant concerning
the swimming pool. Detailed
notes taken by Mr. Murphy of the meeting do not reflect any discussion
with regard to a covenant, and for that matter there was no request by Mr.
Jordan with regards to the swimming pool.
This is confirmed by the two independent
representatives.
To further clarify matters herein, this application for 41
houses is submitted for short term letting in order to qualify under the
Holiday Cottage Tax Breaks. This
holiday cottage tax break is about to expire and to qualify the
application had to be lodged prior to the 30th of May 2003.
This was done, in that the application was lodged on the 28th
of May. The other stipulation
is that all works must be completed before July 2006.
At the time the application was made, that
deadline was the 31st of December 2004. However, section 25 of the Finance Act 2004 extended that
completion period to the 31st of July 2006
Because of the stringency of those deadlines, when the
application was lodged with Cork County Council it was clearly
indicated as part of the submission that the entire development was
going to be built simultaneously i.e. no effective phasing, all
houses and swimming pool and all facilities were to be built together in
order to qualify under the finance act.
The situation herein is quite clear.
This development, if it is to proceed, can be constructed.
There is no second chance. All
deadlines have now passed and the tax breaks that render this development
feasible from an economic point of view are still available but will not
be if this application is refused.
The developer is very disappointed, that after
going to extreme lengths and efforts to satisfy the concerns and
objections raised by Mr. Jordan and to having sent a representative to
meet him to discuss the matter in detail, that Mr. Jordan did not feel
free to contact him by phone or to have his legal representative or his
other agents to make any contact or to return phone calls or
correspondence sent to them before issuing this statement.
The reason that the developer is so disappointed
that Mr. Jordan did not contact him prior to his statement is that a
detailed note of phone numbers was taken by Mr. Jordan, so that such
contacts could be maintained should he have any queries in the future.
The reason that the developer is so disappointed
that Mr. Jordan did not contact him prior to his statement is that a
detailed note of phone numbers was taken by Mr. Jordan, so that such
contacts could be maintained should he have any queries in the future.
Mr. Jordan has stated in his statement to the press and
media and in his objection that his principle concern herein is the
phasing of the development. However,
it is quite clear that had he carried out an inspection of the planners
file, he would have read where Sean Taylor the Executive Planner for the
area clearly stated and I quote from his report as follows; “given that
we have accepted the principle of the proposal, if permission is granted
the following conditions should apply.
The whole development will need to be phased.
I would recommend that the swimming pool/leisure centre is part of
the initial development as this is the area that will have the largest
community benefit.” It is
quite obvious from that report that the reason the phasing was made a
condition was to allow the swimming pool and leisure centre to be built as
part of the initial development. Notwithstanding
the fact that on the 28th of May 2003 the question of phasing
was addressed in our submission when it stated that “all holiday homes
and facilities will be constructed simultaneously”.
The reason for this is the strict deadlines that apply under the
finance act that have been clearly declared above.
Other submissions that have been made to the
local authority in the course of this application are as follows.
A.
The fact that the leisure complex and swimming pool would be open
all year around and would be available to local people has been clearly
indicated.
B.
A free bus link to the local town is also proposed.
C. There is a provision for a bus depot indicated on the
new site layout plan as requested by condition again of the planning
permission granted by Cork County Council, and this is to facilitate
school children being dropped to and from the development.
Also of interest is the fact that this pool was
specifically designed to cater for the Roinn Na Mara requirement of having
a 2 metre depth to facilitate the training of fishermen attending the
local fishery training school.
Finally, in Mr. Jordan’s own
submission, under the first line of the second paragraph it clearly states
and I quote “our client is not opposed in principle to appropriate
development taking place on the site”.
I cannot see anything what is more appropriate to occur on the site
than what is proposed at present. This
site, contrary to Mr. Jordan’s submission, is not idle with 20 years, it
held a publican`s license in 1995.
Secondly, mobile homes and holiday chalets existed on the
site until the year 2000, when the first application was being prepared.
Mr. Jordan has made great play on the swimming pool aspect.
We are now clearly and openly stating that we have no difficulty in
giving any undertaking that Mr. Jordan wishes to have to guarantee the
building of this pool.
The above undertaking is available for Mr. Jordan to
accept at any time and to allow this development to proceed in the
interest of the Beara Peninsula, Tourism and the Local Community, who will
all benefit if this project will go ahead.
If the project will not go ahead, the possibility of gaining such
facilities for the Beara Peninsula again in the future are very slim due
to the demise of the tax scheme that is facilitating this development. |